Window Blinds – First Attempt at Narrowing the Choices Down!!
Image

Entrance Hall and Front Door Looking Good

Window Sill Finishers Beginning to Appear

Jan 25 – Turfing Back Lawns


Jan 24 – Staircase Finished and Glazed
Just a lick of varnish to go !!




Patio Looking Fantastic !!
Patio looking great – the copper porcelain slabs exceed expectation and the laying pattern and accuracy is just perfect. Note how it all changes the way it looks now that the patio level is almost up to DPC level. Amazing difference!!

The team had to work in some dreary wet conditions. Two diamond bladed power cutters helped cut the new slabs quite quickly, but there are many many (!) cuts to make. By 23rd, they had completed the big patio and the pathway behind the dining room.

Needed a little ramp outside the back door threshold.

Tarmac Layer of Drive Goes Down
The tarmac layer went down just fine, but now we have to wait for the weather to clear before the bonded resin surface can go down


Alarm keypad and Panic Button at Front Door
There are two more pin pads – one at back door and other on upstairs landing

Update Saturday Jan 18
This is how the door handles on the bathrooms will be arranged.

Good progress on the patio slabs, the large uncut ones going down first. The random pattern looks great!

This is the new router area of the “plant cupboard”. Router mounted neatly on wall with two cables going up to the study for the MESH network. The square box beneath the router is the Velux controller.

Ensuite of bedroom 2 almost finished

Carpet in new Office is down – needs a clean!!

Nice new loft hatch