Dining Room colour is a little pinkish, but it’s hard to tell in the photo

New fireplace installed today.

Shifting top soil from the front of the property to the rear and levelling up the back garden.

Digging out the new driveway

Sewing Room fully painted

Water Softener arrives and is custom fitted through a hole in the cupboard floor

Handles go in place in the kitchen

Bold Lounge Colouring!!

Towel Rail Conumndrum


Bedroom 1 wardrobes

Dressing Room with airing cupboard on the left

There are light like this on each garage pillar, and on the South east corner. Also wired on the same circuit are the two lights in the porch gable.

This is the amazing little timer to control the front external lights on the building. Its the size of a fuse and sits in the fuse box.



Measuring up for the 680mm towel rail. Bit close!


New cloakroom window – noting chipped tile.


Lounge readiness for Fireplace 2nd fix – due on Dec 16th




No gauge on that pressure dome – I’ll have to ask about that.